OEE Calculator
Free OEE calculator and guide: formula, six big losses, honest benchmarks and an improvement sequence.
Calculator
OEE = Availability × Performance × Quality. The standard metric for equipment productivity: 100 % OEE means producing only good parts, as fast as possible, without stops.
The three factors and the six big losses
| Factor | Formula | Losses it exposes |
|---|---|---|
| Availability | Run time ÷ planned production time | 1. Breakdowns · 2. Setup & adjustments |
| Performance | (Ideal cycle time × total count) ÷ run time | 3. Minor stops & idling · 4. Reduced speed |
| Quality | Good count ÷ total count | 5. Process defects · 6. Startup yield loss |
Benchmarks — read with care
- 100 % — theoretical perfection.
- 85 % — world-class for discrete manufacturing; often used as long-term target.
- 60 % — typical starting point of honestly measured plants (most "reported" OEE numbers are inflated by generous definitions).
More important than the benchmark: measure consistently (same time model, same loss definitions) and attack the biggest loss first — usually availability via setup reduction (SMED).
Improvement sequence that works
- Make losses visible: log stop reasons for 2–4 weeks — no improvement before honest data.
- Attack the top loss: typically setup time or one recurring breakdown cause.
- Stabilise quality: poka-yoke for the top defect mode.
- Then speed: only reduce cycle-time losses once the line runs stable.
Track it with our OEE tracking sheet (CSV) from the template library. Deeper dive on the blog: How to Measure OEE in a Lean Transformation.
Rule of thumb: a 5-point OEE gain on the bottleneck line often frees more capacity than a new machine — at a fraction of the cost.